We are very excited to announce that track construction will shortly commence.
The club has just signed a contract with Begbies Contracting , who will be using the services of Centre State Asphalting. (The same crew who did an excellent job at Wimmera Kart Racing Club)
Wright Civil Engineering have worked closely with Begbies and the grant working group to get the best result for our club.
The track will close for all karting activity from 1 April (AM) until at least 30 June.
The gates will be padlocked during all construction.
Track construction is expected to start shortly after Easter, and is anticipated to take 8-9 weeks.
Despite being Grand Prix weekend, we will need a MAJOR working bee turnout on Saturday 1 April from 8:00am. (BBQ lunch will be provided)
We need this to happen before Easter to make sure the track is ready for contractors to come on site, which will include removing fences and tyres that will enable access to the track.